Before
After
Converting a former logistics office into a specialty practice for Metro Endodontics. We designed and built the interior, from designing the office layout to the final detail cleaning.
Project Overview
Type: Endodontic practice
Location: Willowbrook, IL
Square Footage: 1,850 SF
Project Timeline: 14 weeks
Main Project Goals
- Create a welcoming, comfortable setting for patients and staff.
- Plan the treatment and support spaces around the clinical team’s daily workflow.
- Give the practice a clean, contemporary look.
Scope of Work
- Evaluated the space and developed the floor plan, renderings, and virtual walkthrough.
- Prepared the architectural drawings and handled permit applications.
- Completed interior demolition and the full build-out.
- Designed the interior and selected and installed the finishes, architectural lighting, artwork, and decorative fixtures.
- Installed a central nitrous oxide system and made provisions for a backup generator.
- Built the office IT network and designed and installed a central audio system.
- Designed, fabricated, and installed custom dental cabinetry, office furniture, and the reception desk.
Client Testimonial
From start to finish, Chris and Mike were on top of everything and always had my best interests in mind. They used their extensive experience to prevent unexpected expenses and delays, at the same time adding the little touches that I would not have thought about. I never felt like I had to hover at the construction site because I was confident in their skills and craftsmanship. And I could trust that they would keep me updated on progress and contact me when needed. I can’t say enough about what a pleasure it was to work with such great professionals, and their talent is reflected in my new office. I would choose them again in a heartbeat!
Similar Project
Global Endodontics, Berwyn, IL
Scope of works done:
- Evaluated the space and developed the floor plan, renderings, and virtual walkthrough.
- Prepared the architectural drawings and handled permit applications.
- Completed interior demolition and the full build-out.
- Designed the interior and selected and installed the finishes, architectural lighting, artwork, and decorative fixtures.
- Installed a central nitrous oxide system and made provisions for a backup generator.
- Built the office IT network and designed and installed a central high-definition audio system.
- Designed, fabricated, and installed custom dental cabinetry, office furniture, and the reception desk.